In a program’s definition phase, a program manager in country A is assigned to expand a restaurant chain into country B . The program manager creates the program team by identifying the required project management resources.
Which of the following represents an initial step needed to evaluate available resources that are aligned with the program’s needs?
A . Completing an assessment of skills and competencies
B . Obtaining resource availability information from the functional managers
C . Identifying program resource requirements
D . Creating a program resource management plan
Answer: B