Which of the following project documents should be used to record the occurrence of an unplanned event?
A . Action log
B . Risk log
C . Change log
D . Issue log
Answer: D
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 327