Which of the following prerequisites must be met for the system to check the shelf life of materials at goods receipt? There are 3 correct answers to this question.


Which of the following prerequisites must be met for the system to check the shelf life of materials at goods receipt? There are 3 correct answers to this question.
A . The purchase order item contains the remaining shelf life.
B . The material is managed in batches in the plant.
C . The shelf life expiration date check is activated for the plant in Customizing.
D . The shelf life expiration date check is activated for the material type in Customizing.
E . The shelf life expiration date check is activated for the movement type in Customizing.

Answer: B,C,E