Which of the following parameters should you consider when calculating there order point for a material? There are 3 correct answers to this question.
A . Lot-sizing procedure
B . Expected daily requirements
C . Safety stock
D . Replenishment lead time
E . Checking group for availability check
Answer: B,C,D