Posted by: Pdfprep
Post Date: December 3, 2020
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
A . List of identified risks, potential risk owners, list of potential risk response
B . List of identified risks, list of causes, list of risk categories
C . Short risk titles, list of potential risk owners, list of impacts on objectives
D . List of activities affected, list of potential risk responses, list of causes
Answer: A
Leave a Reply