Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
A . EAC
B . BAC
C . TCPI
D . ETC

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232