IT management has asked for a consolidated view into the organization’s risk profile to enable project prioritization and resource allocation.
Which of the following materials would be MOST helpful?
A . List of key risk indicators
B . Internal audit reports
C . IT risk register
D . List of approved projects
Answer: C