Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

The project manager has noticed a vendor is not performing in accordance with the SLA.

Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

A. Balanced score card

B. WBS

C. Post-project evaluation

D. PERT

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 332