Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?
A . Power interest grid
B . Stakeholder cube
C . Salience model
D . Directions of influence
Answer: C
Explanation:
Reference: https://pmstudycircle.com/2015/09/salience-model-to-analyze-project-stakeholders/