Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?

Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?
A . Power interest grid
B . Stakeholder cube
C . Salience model
D . Directions of influence

Answer: C

Explanation:

Reference: https://pmstudycircle.com/2015/09/salience-model-to-analyze-project-stakeholders/