Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?
A . Power interest grid
B . Stakeholder cube
C . Salience model
D . Directions of influence

Answer: C

Explanation:

Reference: https://pmstudycircle.com/2015/09/salience-model-to-analyze-project-stakeholders/