Which of the following is used as an input to prepare a cost management plan?
A . Expert judgment
B . Lessons learned
C . Cost estimates
D . Project management plan
Answer: D
Explanation:
Reference: https://4squareviews.com/2013/04/30/5th-edition-pmbok-guide-process-7-1-plan-costmanagement/