Which of the following is used as an input to prepare a cost management plan?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which of the following is used as an input to prepare a cost management plan?
A . Expert judgment
B . Lessons learned
C . Cost estimates
D . Project management plan

Answer: D

Explanation:

Reference: https://4squareviews.com/2013/04/30/5th-edition-pmbok-guide-process-7-1-plan-cost­management/