A technician is scheduled to upgrade a grocery store’s network equipment at 11 00 p.m. There are only a few shoppers in the store, therefore, the store manager wants the technician to start the upgrade early.
Which of the following is the NEXT step the technician should perform?
A . Create a back-out plan for the store.
B . Review the change request document
C . Draft the new network diagrams.
D . Get approval from the Change Advisory Board
Answer: D