An IS auditor determines that a business continuity plan has not been reviewed and approved by management.
Which of the following is the MOST significant risk associated with this situation?
A . Continuity planning may be subject to resource constraints.
B . The plan may not be aligned with industry best practice.
C . Critical business processes may not be addressed adequately.
D . The plan has not been reviewed by risk management.
Answer: D