Which of the following is the MOST important consideration when multiple risk practitioners capture risk scenarios in a single risk register?
A . Using a consistent method for risk assessment
B . Developing risk escalation and reporting procedures
C . Maintaining up-to-date risk treatment plans
D . Aligning risk ownership and control ownership
Answer: A