A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?
A . Backlog
B . Standup
C . Kickoff
D . Retrospective
Answer: B
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306