Which of the following is the MOST appropriate responsibility of an IS auditor involved in a data center renovation project?
A . Performing independent reviews of responsible parties engaged in the project
B . Ensuring the project progresses as scheduled and milestones are achieved
C . Performing day-to-day activities to ensure the successful completion of the project
D . Providing sign off on the design of controls for the data center
Answer: A