Which of the following is the FOREMOST root cause of project risk?
Each correct answer represents a complete solution. Choose two.
A . New system is not meeting the user business needs
B . Delay in arrival of resources
C . Lack of discipline in managing the software development process
D . Selection of unsuitable project methodology
Answer: CD
Explanation:
The foremost root cause of project risk is:
– A lack of discipline in managing the software development process
– Selection of a project methodology that is unsuitable to the system being developed
Incorrect Answers:
A: The risk associated with new system is not meeting the user business needs is business risks, not project risk.
B: This is not direct reason of project risk.