PdfPrep.com

Which of the following is the FOREMOST root cause of project risk?

Which of the following is the FOREMOST root cause of project risk?

Each correct answer represents a complete solution. Choose two.
A . New system is not meeting the user business needs
B . Delay in arrival of resources
C . Lack of discipline in managing the software development process
D . Selection of unsuitable project methodology

Answer: CD

Explanation:

The foremost root cause of project risk is:

– A lack of discipline in managing the software development process

– Selection of a project methodology that is unsuitable to the system being developed

Incorrect Answers:

A: The risk associated with new system is not meeting the user business needs is business risks, not project risk.

B: This is not direct reason of project risk.

Exit mobile version