Which of the following is the Business Case used for during the Managing a Stage Boundary process?
A . Enable the Project Board to decide whether or not to authorize the project
B . Justify the continuing viability of the project
C . Enable the Project Board to decide whether or not to authorize project closure
D . Justify the initiation of a project
Answer: B