Management has agreed to perform multiple remediation actions in response to an audit issue, including the implementation of a new control.
Which of the following is the BEST time for an IS auditor to perform an audit follow-up of this issue?
A . After management has completed the required actions
B . When audit resources are available
C . When management resources are available
D . After the new control has been in place for one year
Answer: A