PdfPrep.com

Which of the following is the BEST project management methodology for this requirement?

A customer will have ongoing changes to project requirements.

Which of the following is the BEST project management methodology for this requirement?
A . Waterfall
B . Agile
C . PRINCE2
D . Bottom-up

Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310

Exit mobile version