Which of the following is the BEST key performance indicator (KPI) to measure the effectiveness of a disaster recovery plan (DRP)?
A . Percentage of issues related as a result of DRP testing
B . Number of users that participated in the DRP testing
C . Number of issues identified during DRP testing
D . Percentage of applications that met the RTO during DRP testing
Answer: D