Which of the following is NOT included in the project management triangle?

Posted by: Pdfprep Category: CPIM-SMR Tags: , ,

There are three elements in a project that if you change one you must change one or both of the other two.

Which of the following is NOT included in the project management triangle?
A . People
B . Quality
C . Duration
D . Cost

Answer: A

Explanation:

The project triangle includes project costs, duration, and quality. If you change to a shorter duration you will either need to increase costs or decrease quality. People would be considered a cost in this model since they are charging their time to the project.