Which of the following is NOT designed to deal with risk and uncertainty when planning for time?

Which of the following is NOT designed to deal with risk and uncertainty when planning for time?
A . Project evaluation and review
B . Resource histogram
C . Buffering
D . Scenario Planning

Answer: B