You are a Scrum Master on a project creating an optical fiber cable network across the country. The project has reached the Create User Stories process.
Which of the following is NOT an input to this process?
A . The Prioritized Product Backlog.
B . Identified Risks.
C . Personas.
D . Done Criteria.
Answer: B
Explanation:
The key inputs of creating user stories are Scrum Core Team, Prioritized Product Backlog, Done Criteria, and Personas. The most import tool is User Story Writing Expertise. And the major outputs are User Stories and User Story Acceptance Criteria.
Reference: http://blog.scrumstudy.com/how-are-user-stories-created-in-a-scrum-project/