Which of the following is not an area under Theory of Constraints?
A . Drum Buffer Rope Scheduling
B . Performance Measurements
C . Elimination of Waste
D . Process Tools
Answer: C
Explanation:
Elimination is not under theory of Constraints but in a bigger idea of Lean and JIT. All other choices are areas under Theory of Constraints