Which of the following is NOT a Scrum Master’s responsibility?
A . Groom the Prioritized Product Backlog.
B . Coordinate creation of Release Planning Schedule.
C . Facilitate Prioritized Product Backlog Review Meetings.
D . Represent the Scrum Core Team to provide lessons from the project.
Answer: A
Explanation:
The prime responsibilities of a Scrum Master are:
Removes the obstacles/impediments that affect productivity.
Shields the people from external disturbance.
Responsible if the scrum process is correctly applied.
Facilitate daily stand-ups, other ceremonies, schedule meetings, demo and other meetings.
Help product owner in prioritizing the backlog and any feedback from the team.
Facilitation of Retrospective meetings
Workshops for planning, estimation, prioritization, issue resolution, performance improvements
Reference: https://www.knowledgehut.com/interview-QUESTION NO:s/scrum
Leave a Reply