Which of the following is NOT a purpose of the Closing a Project process?
A . Plan the activities required to close a project
B . Enable a comparison of the original objectives of a project against what was actually achieved
C . Enable premature closure if the Project Board request that a project should no longer continue
D . Provide a fixed point at which acceptance for the project product is confirmed
Answer: A