A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference.
Which of the following is MOST likely to be the main challenge the influences this decision?
A . Geographical factors
B . Language barriers
C . Cultural differences
D . Technology factors
Answer: A
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 259