Which of the following is MOST important for maintaining the effectiveness of an IT risk register?
A . Recording and tracking the status of risk response plans within the register.
B . Communicating the register to key stakeholders.
C . Performing regular reviews and updates to the register.
D . Removing entries from the register after the risk has been treated.
Answer: C