Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit

Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit
A . Brainstorming
B . Inspections
C . Expert interviews
D . Independent assessments

Answer: B