Which of the following is FALSE regarding an Exception Report?
A . It describes a forecast deviation of stage or project level tolerance
B . It contains recovery options and a recommendation
C . It replaces a Stage Plan or Project Plan
D . It describes the consequences of the deviation
Answer: C