Which of the following is carried out as part of the Initiating a Project process?

Which of the following is carried out as part of the Initiating a Project process?
A . Ensure there is authority to deliver the project’s products
B . Ensure there is a common understanding of the reasons for doing the project
C . Appoint the Executive and Project Manager
D . Create a stage Plan for the next stage of the project

Answer: B