Which of the following is an acceptable method for handling positive project risk?

Which of the following is an acceptable method for handling positive project risk?
A . Exploit
B . Avoid
C . Mitigate
D . Transfer

Answer: A

Explanation:

Exploit is a method for handling positive project risk.

Incorrect Answers:

B, C, D: These are all responses which is used for negative risks, and not the positive risk.