Which of the following is a tool and technique for Estimate Activity Durations?

Which of the following is a tool and technique for Estimate Activity Durations?
A .  Parametric estimating
B .  Monte Carlo analysis
C .  Alternatives analysis
D .  Bottom-up estimating

Answer: A