Which of the following is a security project risk?

Following a successful and well-publicized hacking incident, an organization has plans to improve application security.

Which of the following is a security project risk?
A . Critical evidence may be lost.
B . The reputation of the organization may be damaged.
C . A trapdoor may have been installed in the application.
D . Resources may not be available to support the implementation.

Answer: D