Which of the following is a relevant cost?
A . A sunk cost
B . A committed cost
C . An incremental cost
D . A historical cost
Answer: C
Explanation:
Reference: https://www.acowtancy.com/textbook/cima-p1-2015/c1-relevant-costing/concept-of-relevant-costing/notes