PdfPrep.com

Which of the following is a relevant cost?

Which of the following is a relevant cost?
A . A sunk cost
B . A committed cost
C . An incremental cost
D . A historical cost

Answer: C

Explanation:

Reference: https://www.acowtancy.com/textbook/cima-p1-2015/c1-relevant-costing/concept-of-relevant-costing/notes

Exit mobile version