A project manager needs to track the actual and estimated start and finish dates of all WBS work packages.
Which of the following is a necessary step to record the actual durations?
A . Establish each WBS work package resource.
B . Establish and set the baseline.
C . Establish and set the quality gates.
D . Establish the tollgates.
Answer: B
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 167