Which of the following is a MAJOR task of evaluating exit criteria and reporting?
A . Writing a test summary report for stakeholders
B . Logging the outcome of test execution
C . Repeating test activities as a result of action taken for each discrepancy.
D . Evaluating testability of the requirements and system
Answer: A