Which of the following implementations of a continuous monitoring risk mitigation strategy is correct?
A . Audit successful and failed events, transfer logs to a centralized server, institute computer assisted audit reduction, and email alerts to NOC staff hourly.
B . Audit successful and critical failed events, transfer logs to a centralized server once a month, tailor logged event thresholds to meet organization goals, and display alerts in real time when thresholds are approached.
C . Audit successful and failed events, transfer logs to a centralized server, institute computer assisted audit reduction, tailor logged event thresholds to meet organization goals, and display alerts in real time when thresholds are exceeded.
D . Audit failed events only, transfer logs to a centralized server, implement manual audit reduction, tailor logged event thresholds to meet organization goals, and display alerts in real time when thresholds are approached and exceeded.
Answer: C