Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?

A critical stakeholder has requested additional status updated beyond the schedule.

Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?
A . Confidentiality
B . Criticality
C . Frequency
D . Cultural differences

Answer: C

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 265