PdfPrep.com

Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.)

Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.)
A . Business continuity response
B . Milestone achievement
C . Incident response
D . Schedule change
E . Change request
F . Stakeholder changes

Answer: A,B

Exit mobile version