Posted by: Pdfprep
Post Date: September 27, 2021
Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.)
A . Business continuity response
B . Milestone achievement
C . Incident response
D . Schedule change
E . Change request
F . Stakeholder changes
Answer: A,B
Leave a Reply