Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes?

A stakeholder is unaware of a project’s status.

Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
A . Status report
B . Organizational chart
C . RACI matrix
D . Meeting minutes
E . Communication plan

Answer: AD

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261