Which of the following descriptions about the LAA technical is wrong?
A . RLC layer controls activation of unlicensed spectrum
B . Unlicensed spectrum resources are centrally scheduled and allocated by the base station
C . Authorized spectrum as the primary carrier
D . Improve network capacity
Answer: A