Which of the following describes a burn rate?
A . The rate at which project documents are disposed.
B . The rate at which project personnel leave the project.
C . The rate at which the project budget is used.
D . The rate at which the timeline increases.
Answer: C
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232