A program manager at a pharmaceutical company plans a new drug development effort . The development is slated to yield three drug variants . The program manager articulates the program scope boundaries.

Which of the following deliverables captures these items?
A . Program scope management plan
B . Program governance plan
C . Program scope statement
D . Program work breakdown structure

Answer: C