Due to an emergency situation, a customer needs to activate all processor and memory resources in a Power System E980 for ten days.
Which of the following could be used to achieve this need with the least possible cost?
A . Elastic CoD
B . Trial CoD
C . Utility CoD
D . Static Activation
Answer: A