A project manager is implementing a new edition of a magazine with an end-of-the-week deadline. The design analyst notices two main articles were not included, as requested by the client.
Which of the following constraints should be considered FIRST?
A . Scope
B . Quality
C . Time
D . Budget
Answer: C