During the follow-up phase the following conditions are checked:
X1. The code has been completely reviewed
X2. All the identified defects have been correctly fixed and the modified code has been compiled successfully and run through all the static analyzers used by the project without warnings and errors
X3. The modified code is available under the configuration management system with a new version number for the specified CI
If these conditions are fulfilled then the review process terminates.
Which of the following characteristics of a formal review is missing in this description? K2 1 credit
A . Defined entry and exit criteria
B . Checklists to be used by the reviewers
C . Deliverables such as reports, evaluation sheets or other review summary sheets
D . Metrics for reporting on the review effectiveness, efficiency, and progress
Answer: D